July 2025 Grantee Project Update: One Year In—Momentum Continues to Build!

We’re excited to provide an update on our project journey! With 35 active projects now underway, the impact is growing and the momentum remains strong.

📌 Key Highlights
All 35 projects are operational.
• Project Milestones:
• 2 projects are in Milestone 1
• 23 projects have progressed to Milestone 2
• 9 are in Milestone 3
• 1 project has reached Milestone 4

⏱ Grantee Project Timeline Stats
• Total days across all projects: 15,249
• Average project duration: 436 days
• Fastest project: 283 days
• Longest project: 485 days

📊 Progress Snapshot
• Total days completed: 7,657
• Average days completed per project: 226
• Most progressed project: 86% complete
• Overall average completion: 52%

🌱 Grantee Project Types
• On-ground initiatives: 27
• Education-focused projects: 6
• Combined efforts (on-ground + education): 2

🧑‍🏫 Events & Workshops
As part of their project delivery, many grantees are actively engaging their communities through events and workshops focused on environmental education, awareness, and training.
Current status:
• To be scheduled: 10
• In development: 19
• Completed: 13
Completed By Catchment:
• Brunswick: 1
• Clarence: 3
• Richmond: 9

🌿 Combined Grantee Project Outputs (So Far!)
These figures represent the tangible on-ground results delivered by our incredible grantee teams:
• Length of riverbank restored: 9.20 km
• Area revegetated: 25.37 hectares
• People educated/trained/informed: 909
• Students educated/trained/informed: 214
• Trees and sedges planted: 24,707
• Exclusion fencing installed: 4,233.8 meters
• No of Photo Point records submitted: 212

This remarkable progress is a testament to the dedication, resilience, and collaborative spirit of everyone involved. With many projects now well beyond the halfway mark, we are confident that we’re on track to meet—and likely exceed—our core goal:

Stay tuned as we continue to share stories, stats, and successes from the field!